Existing 330kV lines
The physical flows of electricity shown on the map are technical transit flows that enter the power system across one border and leave the power system across another border. Technical transit flows are not an indicator for commercial supplies.
Existing 330kV lines
On 9 January 2025, exactly a month before the Baltic States join the European energy system (synchronisation), the first synchronous condenser station in Latvia was connected to the power…
In February 2025, the energy systems of the Baltic States will disconnect from Russia's energy system and join the energy system of continental Europe, which is three times bigger than Russia's…
AS "Augstsprieguma tīkls" together with the other Baltic TSOs – Litgrid AB and Elering AS, and the TSOs of the Baltic Capacity Calculation Region (CCR) have jointly developed proposals necessary…
To further enhance the efficiency of Latvia’s transmission system operator JSC “Augstsprieguma tīkls” (AST), its shareholder – the Ministry of Climate and Energy – has decided to further reduce…